Lift Station Failure Released Untreated Sewage

City confirms 100,000 gallons of sewage escaped lift station Another 100,000 gallons collected inside facility; Wells 9 and 9A being monitored and sampled
Lift Station Failure Released Untreated Sewage
Erosion damaged property to the south of the East Lift Station.

Author: Rachel Dahl

The City of Fernley has confirmed that approximately 100,000 gallons of untreated wastewater escaped the East Lift Station Friday, Sept. 11, crossed an adjacent parcel of land and traveled along a railroad embankment, contradicting an earlier public characterization that the spill had been contained.

Another estimated 100,000 gallons accumulated in the basement of the lift station, bringing the total involved in the incident to approximately 200,000 gallons, according to a city statement released Tuesday.

Nevada Division of Environmental Protection Environmental Assistance and Certification Program Coordinator Zachary Lamebull provided the incident report filed by Ozzie Henke, the City of Fernley Utilities Director, which confirms the 200,000-gallon estimate was reported by the City of Fernley at 8:43 a.m. Friday morning.

The city press release said Q&D Construction notified the City at approximately 6 a.m. Friday that water was coming out of the East Lift Station and traveling south onto neighboring property.

“Wastewater flowed out past the building onto a vacant lot south and down the east side of the rail spur, causing some erosion along the access road and spur line,” the release said.

Photographs taken after the spill show a deep erosion channel cut alongside the railroad embankment, with displaced rock and soil extending away from the lift station.

The city said emergency bypass pumping was fully operational by 2:30 p.m. Friday, restoring normal flow from the collection system to the wastewater treatment plant. Water trucks carrying chlorinated water were used to treat exposed soil.

The city’s account clarifies that the wastewater was not contained within the lift-station property.

In a comment posted Saturday in response to The Reporter’s original story, City Councilman Albert Torres wrote that the incident involved an underground structural break.

“It was contained, and is being cleaned up,” Torres wrote. “The City and the State will do inspections and will make sure everything is cleaned up, decontaminated and the property owner is made whole.”

The city’s Tuesday statement acknowledges that approximately half of the estimated wastewater left the facility, crossed neighboring property and caused erosion along the railroad infrastructure.

The city did not officially respond to several requests for information regarding the spill until Tuesday when they release the detailed public statement four days after the failure.

An internal report prepared Friday by Chief Operating Officer Barry Williams for the mayor and City Council described the incident as a “catastrophic failure” involving critical city infrastructure.

The report said wastewater accumulated in the lift-station basement and caused erosion to portions of the embankment supporting a rail spur owned by Mark IV Capital. It said Premier Construction had been retained to inspect the embankment, determine the extent of the damage and perform repairs.

The internal report did not provide a spill estimate, identify the lift station by name or address the possible effect on nearby municipal wells.

It also differs from Tuesday’s release concerning how the problem was discovered. The internal report says city staff identified the failure, while the public release says Q&D notified the city at approximately 6 a.m.

The internal report said the city notified its insurance carrier immediately and initiated a claim. Potential costs include emergency contractors, bypass pumping, cleanup, equipment repair or replacement and stabilization of the railroad embankment. No cost estimate has been released.

The cause remains unknown. The basement must be emptied before pumps, motors, electrical systems, controls, instrumentation and structural components can be inspected, according to the internal report.

The city anticipated completing removal of wastewater from the basement Tuesday. It said an engineer and licensed cleanup team would then inspect the building, clean the facility and collect soil samples. Any soil found to be contaminated would be removed and disposed of.

The East Lift Station sits near municipal Wells 9 and 9A, and the city notice said neither well was affected by the failure and stated that there was “no threat to the public.” It also said both wells would be monitored and sampled “in an abundance of caution.”

The release does not say whether either well was taken out of service, when samples would be collected, what contaminants would be tested or whether results were available before the city concluded the wells were unaffected.

The city said water from both wells is chlorinated before being sent to the Water Treatment Plant, where it is treated again before entering the potable-water system.

The city also said the NDEP and its Bureau of Water Pollution Control were notified within an hour of the failure. It has not released the time of that notification or the initial report submitted to regulators.

City records identify Nathan McIntyre as Fernley’s wastewater systems foreman. McIntyre is the son of Mayor Neal McIntyre and prepares the wastewater division’s monthly operational reports. A report dated Jan. 5 stated that daily rounds and inspections of the East Lift Station were completed during December 2025.

The city has not said when the station was last inspected before Friday’s failure, whether earlier inspections identified structural or mechanical concerns, or what maintenance had been performed on the failed equipment.

The City Council adopted a new Sewer Master Plan in August identifying approximately $7.61 million in existing maintenance and repair needs. The listed projects included a $2.97 million East Lift Station and force-main project.

The city’s internal report says a later update will identify the confirmed cause, damage, repair plan, costs, insurance coverage, restoration timeline and any corrective improvements recommended to prevent another failure.

The Fernley Reporter will update this story when NDEP provides its response concerning Wells 9 and 9A and when sampling results and additional incident records become available.

 


Share
Rate

Comment

Comments

P 09/16/2026 10:31 PM
Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS.

COMMENTS
Comment author: John Mueller Comment text: FERNLEY’S WATER EMERGENCY: FIVE QUESTIONS STILL NEED ANSWERS The November 12 Fernley Reporter article provides a good recap of the November 3 water emergency and the November 4 City Council meeting. First, credit where credit is due. Our city employees responded, restored operations, and took precautions to protect residents. That’s important and appreciated. But fixing the immediate problem isn’t the same as preventing it from happening again. There are five reasonable questions our community deserves answers to: 1. WHAT ACTUALLY FAILED? What was the root cause of the water treatment plant’s communication failure, and why didn’t the backup systems prevent the interruption? 2. HOW CLOSE WERE WE TO A REAL EMERGENCY? How much usable water remained in storage, and how close did we come to affecting essential services, including firefighting? 3. WHAT WILL THIS COST TAXPAYERS AND RATEPAYERS? What did the emergency cost, what additional repairs or upgrades are necessary, and how will they be funded? 4. WHO IS RESPONSIBLE FOR MAKING SURE IT DOESN’T HAPPEN AGAIN? Is there a written corrective-action plan with assigned responsibilities, measurable results, and completion deadlines? 5. HOW WILL RESIDENTS KNOW THE PROBLEM IS REALLY FIXED? Will the city publish an after-action report explaining what happened, what was learned, what has been corrected, and what still needs attention? This isn’t about pointing fingers or finding someone to blame. It’s about learning, improving, and protecting our community. We can appreciate the city’s response while still expecting transparency, accountability, and a commitment to continuous improvement. Some technical information may need to remain confidential for security reasons. But that shouldn’t prevent residents from understanding the risks, the corrective actions, and the results. The real question isn’t whether Fernley recovered from the November 3 emergency. We know it did. The question is: If the same failure happened tomorrow, would we be better prepared? That’s a conversation worth having. Our community deserves more than reassurance. It deserves measurable results. Comment publication date: 11/12/26, 1:54 PM Comment source: Fernley Council Addresses Water Emergency Comment author: Donald DeVold Comment text: Great article It’s actually spelled DeVold Thank you Comment publication date: 10/29/26, 4:58 PM Comment source: The great robbery: Strip-6 by Solis helps Vaqueros punch playoff ticket Comment author: CH Comment text: I want to start a betting 'pool' for the October, November, and December closures: 1. A dent in the pool slide. 2. A failed breaker. 3. A pebble loose in the water part (replacing all concrete) 4. Hurricane Polo makes a sudden turn and blows off the roof (again). With soft muscles after 7 months of no swimming, the only health left is my sense of humor :) Comment publication date: 10/1/26, 11:18 AM Comment source: Fernley Pool Renovation Moves Forward, One Test at a Time Comment author: PFB Comment text: Why can't you guys find competent contractors.. For a large municipal facility like the indoor-outdoor Fernley Swimming Pool located at 300 Cottonwood Lane, a complete ground-up commercial build or major structural renovation typically spans 6 to 12 months or longer when factoring in large-scale engineering, public municipal permitting, specialized commercial HVAC/roofing, and health department inspections. The current renovation has been- The Fernley Swimming Pool has been closed for approximately six to seven months since late February 2026 for a major roof replacement and facility renovation. Now you sat October. Soooo 8 months for a new roof. The picture shows no other renovations. Comment publication date: 9/17/26, 7:14 PM Comment source: Electrical problem delays Fernley pool opening Comment author: P Comment text: Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS. Comment publication date: 9/16/26, 10:31 PM Comment source: Lift Station Failure Released Untreated Sewage Comment author: Christopher Walsh Comment text: Could you look into the strong recurring smell around Fernley? It smells like sewage and it can be bad enough that people don’t want to be outside or open their windows. It would be helpful to get an investigative journalist help the Fernley residents get a clear answer from the City, NDEP, and any involved facilities. I was really disappointed that the smell was not disclosed by my realtor when I moved here. I enjoy Fernley and am seeing the improvements that are being made. With Appreciation Comment publication date: 9/12/26, 2:49 PM Comment source: Sewage spill near City of Fernley Municipal Well 9