Tract, developers of data-storage centers, plans huge investment into Storey County facilities in next decade, CEO van Rooyen says

Tract, developers of data-storage centers, plans huge investment into Storey County facilities in next decade, CEO van Rooyen says

Tract, a company based in Denver, Colo., which develops master plans and builds infrastructure for data-storage centers, will invest $100 billion into  Storey County over the next 10 years, CEO Grant van Rooyen said recently on Nevada Newsmakers.

Van Rooyen told host Sam Shad that his company has already secured thousands of acres of land and large amounts of power and water for the planned growth of the data-storage centers just east of Reno and Sparks.

"We have 11,000 acres," van Rooyen said. "We've also procured, under contract, 2,025 megawatts. That's just over two gigawatts of electricity.

"And by the time we've fulfilled the construction and the development that goes along with utilizing that two gigawatts, the total development value, or the capital involvement bringing that to life, will be approximately $100 billion," he said.

"I'll say that again, $100 billion," van Rooyen added.

A gigawatt is 1 billion watts, enough juice to power 876,000 homes for one year, according to estimates.

Veteran Nevadan Journalist Ray Hagar is known for fair and tough reporting and invigorating commentary.


Recently, Tract purchased almost 9,000 acres at the Tahoe-Reno Industrial Complex (TRI) to complete its current land acquisitions in Storey County. About a quarter of Tract's overall investment will go to data-center infrastructure needs, van Rooyen said.

"About $25 billion of that will be concrete, steel, mechanical and electrical infrastructure that constitutes the buildings," he said. "Those are massive construction projects. Those come with a huge number of good, high paying jobs. And, that is development that'll occur over possibly a 10-year period."

Many factors were considered before investing so heavily in Storey County, van Rooyen said.

"The first thing I would observe is data centers can't just be located anywhere," he said. "They have a number of criteria that are very responsive to development.

"Proximity to fiber networks is critical," he said. "And very early in my career, I was participating with a very talented group of individuals and we built the largest fiber network in the United States. And one of those routes comes down I-80 (Interstate 80) and so we remember that fondly.

"Availability of power, electricity is very important, as is the price of that electricity," he said.

Van Rooyen added that the I-80 corridor is also ideal because of it's "proximity to an end user base -- those who are going to consume these resources that exist in these data centers."

He said the area also has "a talented workforce that can participate in developing them, building them and operating them."

He also praised Storey County for being a "very pro-business environment at both the political and the economic level."

The nimbleness of Storey County government gives the company "the ability to move with speed and certainty," he said.

"We found that in Storey County," he said. "The rules are clear. We can pull a building permit within 30 days. We can pull a grading permit within seven days. And those characteristics really, really matter with that magnitude of development."

Tract's job is to take care of all the infrastructure and building needs to allow a data-storage company to come into a Northern Nevada site and open for business "almost immediately," van Rooyen said.

"We don't just buy land. We also contract for that electricity. We post surety with our utility partners," van Rooyen said. "We buy transformers and with long lead time, electrical infrastructure.

"And we create roads," he continued. "We extend wet infrastructure, water and sewer. We buy water. We facilitate the availability of that water on site, and we deliver graded, prepared pads, such that a vertical developer can come along, transact with us and be in a position to start building almost immediately."

Because of the growing data-storage industry, Northern Nevada's energy usage is expected to double in the next decade, NV Energy President and CEO Doug Cannon said recently on Nevada Newsmakers.

Van Rooyen said Tract developments will use multiple energy sources.

"First year at a macro level, our entire industry is appropriately committed to the pursuit of net zero and embracing all forms of renewable energy," he said. "That's a long-term goal and the delivering on that objective is going to require the entire energy mix," van Rooyen said.

"Net zero" is a target of completely negating the amount of greenhouse gasses produced by human activity, according to an Oxford dictionary definition.

However, data-storage centers need a constant source of energy that can't be interrupted so energy redundancies are built into projects.

"It is fair to say that the energy transition we need to go through is also very complicated and data centers require firm power," he said. "They can't turn on and off for eight hours a day at a time when the sun shining or the wind's blowing. And so the choreography of that energy mix is crucial."

Water, or the lack of it, has traditionally been a limiting factor for economic growth in Northern Nevada. But Van Rooyen said Tract already has the water for the first phase of development.

"We are currently one of the largest owners of water in TRI," he said. "We made those purchases a couple of years ago, both potable and processed water."

He later added: "So, yes, we have what (water) we need. And we have a little bit more than we need, as an insurance policy."

Watch this episode of Nevada Newsmakers.

See the upcoming schedule for Nevada Newsmakers.

Share
Rate

Comment

Comments

COMMENTS
Comment author: CH Comment text: I want to start a betting 'pool' for the October, November, and December closures: 1. A dent in the pool slide. 2. A failed breaker. 3. A pebble loose in the water part (replacing all concrete) 4. Hurricane Polo makes a sudden turn and blows off the roof (again). With soft muscles after 7 months of no swimming, the only health left is my sense of humor :) Comment publication date: 10/1/26, 11:18 AM Comment source: Fernley Pool Renovation Moves Forward, One Test at a Time Comment author: PFB Comment text: Why can't you guys find competent contractors.. For a large municipal facility like the indoor-outdoor Fernley Swimming Pool located at 300 Cottonwood Lane, a complete ground-up commercial build or major structural renovation typically spans 6 to 12 months or longer when factoring in large-scale engineering, public municipal permitting, specialized commercial HVAC/roofing, and health department inspections. The current renovation has been- The Fernley Swimming Pool has been closed for approximately six to seven months since late February 2026 for a major roof replacement and facility renovation. Now you sat October. Soooo 8 months for a new roof. The picture shows no other renovations. Comment publication date: 9/17/26, 7:14 PM Comment source: Electrical problem delays Fernley pool opening Comment author: P Comment text: Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS. Comment publication date: 9/16/26, 10:31 PM Comment source: Lift Station Failure Released Untreated Sewage Comment author: Christopher Walsh Comment text: Could you look into the strong recurring smell around Fernley? It smells like sewage and it can be bad enough that people don’t want to be outside or open their windows. It would be helpful to get an investigative journalist help the Fernley residents get a clear answer from the City, NDEP, and any involved facilities. I was really disappointed that the smell was not disclosed by my realtor when I moved here. I enjoy Fernley and am seeing the improvements that are being made. With Appreciation Comment publication date: 9/12/26, 2:49 PM Comment source: Sewage spill near City of Fernley Municipal Well 9 Comment author: Alicia Euresti Comment text: We are all so blessed to have Pastor Matt and Mrs. Regina in this town. They have become a major part of pur family and our children adore them. Thank you both for all you do for qll of us. We love you!!!! Comment publication date: 9/6/26, 9:24 PM Comment source: Fascinating Fernley: Meet Your Neighbors at Living Faith Food Pantry Comment author: R Conley Comment text: Is the deputy receiving any additional training or reinforcing prior training? Comment publication date: 9/5/26, 10:08 AM Comment source: Inmate escapes from Fernley substation