Fernley residents concerned as wells run dry and canal lining project extends

Fernley residents concerned as wells run dry and canal lining project extends
Construction continues on concrete canal lining. Photo courtesy of the BOR.


By Leanna Lehman, For the Fernley Reporter

The TCID Board met Thursday, Aug. 17, along with representatives from the Bureau of Reclamation (BOR) and several members of the public to discuss extending the outage of the Truckee Canal in Fernley for 30 days to accommodate delays in the project due to poor weather conditions.

The 31-mile-long canal delivers water to more than 50,000 acres of farmland, wildlife, and area residents. The earthen canal breached in January 2008 caused flooding and millions in damage to properties and homes in Fernley.

Phase I of the Truckee Canal Public Safety Improvement Project began last December. The multiphase federally funded project aims to restore the safe, long-term operation of the Truckee Canal, increase public safety, and improve water supply reliability. The canal extends from the Truckee River through Fernley and into Lahontan Reservoir. TCID and BOR shut down the canal last fall before construction, and it has remained inactive so that concrete lining can be installed through approximately 3.5 miles of the earthen canal in the most vulnerable stretch to the City of Fernley.

According to the contract, the agreed upon construction window for the canal outage (no water flow) is October 1, 2022, through September 30, 2023, with a provision for a 30-day extension if mutually agreed upon by TCID and the BOR Contracting Officer.

According to BOR Lahontan Basin Area Office Manager Jack Worsley, the entire project, which includes additional maintenance that can be done with water in the canal, is expected to be completed by March or April 2024, which is the initially anticipated completion date. More present concerns, however, revolve around the canal outage and the rapidly dropping water table in areas believed to be affected.

Fernley residents that attended the meeting came with questions but received few answers. When asked about seeing the project plans and details about the construction specifications in hopes of understanding why the delay, they were told by Worsley that they do not have to provide those details to the public as they are not a matter of public record. It was later disclosed that even TCID could not access the plans.

“BOR does not release designs for projects,” Worsley said, “We don’t do that.”

It was later stated that BOR is a “quasi-public agency.”

Some Fernley residents stated they have had to deepen their wells and are dealing with limited water due to the canal being out of service since last fall. Residents believe that their wells have run dry as a result. Jim Moffit reported that he has had to deepen his well, which carries a hefty price tag of $20,000. Drillers had to deepen to 300’ after coming up dry at 180’ and 240’. He also told the board that several of his neighbors must extend the depth of their wells.

One resident pressed Worsley stating that during the August 1 meeting, the BOR was asked how much of the lining was completed, to which he replied at the time, “I don’t have that,” but stated he would find out. Worsley again did not have an answer.

According to Worsley, the contract has a built-in provision to extend for weather delays, so they are asking for the extension. One resident stated that she had no confidence that the project would be done at the end of the 30 days extension.

“I guarantee you the project is not going to be done on October 30. You sat right here on August 1 and told us there were no delays reported.” Worsley’s response was, “I couldn’t say anything else.”

It was later explained that when it rains, the canal takes a very long time to dry so the work can continue, which has resulted in delays. According to Worsley, the weather exceeded the allowed time outlined in the contract, but should the matter go to court; a judge would likely rule in favor of the contractor as the weather conditions are out of their control. However, the question remained unanswered as to why this was not disclosed at the August 1 meeting.

TCID Board Member Davey Stix asked the BOR, “So let's say we grant the 30 days, and November 1st rolls around, and the contractors are not done? Does anyone have an answer at all if this extension is denied?” Worsley replied, “You’re not going to be able to put water in the canal.” The project cannot be completed if the extension is not granted.

Fernley Mayor Neal E. McIntyre also had questions. “I don’t know what the process was for getting the contract, beginning of the project. I have been in construction for 40 years, and it comes down to why are we contracting with a company from Alaska that doesn’t know how to move dirt?”

He also stated that there have already been three superintendents on the job.

“This is the primary reason that we are where we are on this job. Now, we are not anywhere close to being done,” said McIntyre. “You’ve got two months to do two miles, and it’s taken you 10 months to do a mile. I think that’s a really big problem.”

He further stated that they were led to believe the outage would not affect the aquifer, but it has. Fernley has wells that are going dry and many people that don’t have the money to deepen.

“This is really detrimental to the citizens of Fernley,” McIntyre said.

Worsley, who did not realize the speaker was the mayor of Fernley, asked, “So you’re the one suing us with the “stop work”? – I can’t really talk to you about this.”

Steven Macky, another Fernley resident, asked how soon the water would be back in the canal if they got the 30-day extension. He was told that the BOR cannot give a firm time, but it depends on many factors.

“We are doing everything we can to get that water back in. If there is an injunction right now, there will be no water delivered to Fernley through the takeout. We are doing everything we can; we are. We need to make sure the canal can take water safely and that we can make deliveries, said Worsley, “Nobody is sitting around this table trying to say Fernley can suck it.”

Public comments continued for nearly an hour as Fernley water users expressed frustration and sought definitive answers. Unfortunately, the only clear answer was that failing to extend the contract for 30 days would slow the project and only delay water being returned to the canal. The TCID Board approved the extension with promises of further discussion at the September meeting.

Share
Rate

Comment

Comments

COMMENTS
Comment author: John Mueller Comment text: FERNLEY’S WATER EMERGENCY: FIVE QUESTIONS STILL NEED ANSWERS The November 12 Fernley Reporter article provides a good recap of the November 3 water emergency and the November 4 City Council meeting. First, credit where credit is due. Our city employees responded, restored operations, and took precautions to protect residents. That’s important and appreciated. But fixing the immediate problem isn’t the same as preventing it from happening again. There are five reasonable questions our community deserves answers to: 1. WHAT ACTUALLY FAILED? What was the root cause of the water treatment plant’s communication failure, and why didn’t the backup systems prevent the interruption? 2. HOW CLOSE WERE WE TO A REAL EMERGENCY? How much usable water remained in storage, and how close did we come to affecting essential services, including firefighting? 3. WHAT WILL THIS COST TAXPAYERS AND RATEPAYERS? What did the emergency cost, what additional repairs or upgrades are necessary, and how will they be funded? 4. WHO IS RESPONSIBLE FOR MAKING SURE IT DOESN’T HAPPEN AGAIN? Is there a written corrective-action plan with assigned responsibilities, measurable results, and completion deadlines? 5. HOW WILL RESIDENTS KNOW THE PROBLEM IS REALLY FIXED? Will the city publish an after-action report explaining what happened, what was learned, what has been corrected, and what still needs attention? This isn’t about pointing fingers or finding someone to blame. It’s about learning, improving, and protecting our community. We can appreciate the city’s response while still expecting transparency, accountability, and a commitment to continuous improvement. Some technical information may need to remain confidential for security reasons. But that shouldn’t prevent residents from understanding the risks, the corrective actions, and the results. The real question isn’t whether Fernley recovered from the November 3 emergency. We know it did. The question is: If the same failure happened tomorrow, would we be better prepared? That’s a conversation worth having. Our community deserves more than reassurance. It deserves measurable results. Comment publication date: 11/12/26, 1:54 PM Comment source: Fernley Council Addresses Water Emergency Comment author: Donald DeVold Comment text: Great article It’s actually spelled DeVold Thank you Comment publication date: 10/29/26, 4:58 PM Comment source: The great robbery: Strip-6 by Solis helps Vaqueros punch playoff ticket Comment author: CH Comment text: I want to start a betting 'pool' for the October, November, and December closures: 1. A dent in the pool slide. 2. A failed breaker. 3. A pebble loose in the water part (replacing all concrete) 4. Hurricane Polo makes a sudden turn and blows off the roof (again). With soft muscles after 7 months of no swimming, the only health left is my sense of humor :) Comment publication date: 10/1/26, 11:18 AM Comment source: Fernley Pool Renovation Moves Forward, One Test at a Time Comment author: PFB Comment text: Why can't you guys find competent contractors.. For a large municipal facility like the indoor-outdoor Fernley Swimming Pool located at 300 Cottonwood Lane, a complete ground-up commercial build or major structural renovation typically spans 6 to 12 months or longer when factoring in large-scale engineering, public municipal permitting, specialized commercial HVAC/roofing, and health department inspections. The current renovation has been- The Fernley Swimming Pool has been closed for approximately six to seven months since late February 2026 for a major roof replacement and facility renovation. Now you sat October. Soooo 8 months for a new roof. The picture shows no other renovations. Comment publication date: 9/17/26, 7:14 PM Comment source: Electrical problem delays Fernley pool opening Comment author: P Comment text: Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS. Comment publication date: 9/16/26, 10:31 PM Comment source: Lift Station Failure Released Untreated Sewage Comment author: Christopher Walsh Comment text: Could you look into the strong recurring smell around Fernley? It smells like sewage and it can be bad enough that people don’t want to be outside or open their windows. It would be helpful to get an investigative journalist help the Fernley residents get a clear answer from the City, NDEP, and any involved facilities. I was really disappointed that the smell was not disclosed by my realtor when I moved here. I enjoy Fernley and am seeing the improvements that are being made. With Appreciation Comment publication date: 9/12/26, 2:49 PM Comment source: Sewage spill near City of Fernley Municipal Well 9