Go to main contentsGo to main menu
Thursday, October 1, 2026 at 2:59 PM

NDOT to begin construction on I-80 bridges Jan. 16

NDOT to begin construction on I-80 bridges Jan. 16

Robert Perea, The Fernley Reporters

Drivers heading into and out of Fernley should be prepared for delays for the next year as the Nevada Department of Transportation begins its project to renovate bridges and overpasses on Interstate 80.

Lane reductions and traffic switches begin Jan. 16 on Interstate 80 and interstate underpasses in Fernley and Wadsworth as part of a year-long Nevada Department of Transportation project to retrofit interstate bridges. 

Interstate traffic will still be able to travel through the area, with minor travel delays and vehicle width restrictions. Street and lane closures will also take place on interchanges below the interstate.

Interstate 80 • I-80 reduced to one lane in each direction between exits 43-48 (east Fernley to Wadsworth). Lane shifts and temporary traffic crossovers will be in place 24-7 beginning Jan. 16 through the end of 2023. • Reduced speeds of 55mph will be in place in this area of interstate. 

Wadsworth Cantlon Drive/Main Street (Wadsworth Exit 43)• Southbound Cantlon Drive/Main Street closed underneath I-80 beginning Jan. 16 through summer 2023, with a local detour available. • Northbound traffic will still be able to travel underneath the interstate. 

Fernley I-80 Vine Street Underpass• Vine Street closed underneath I-80 beginning Jan. 16 through early summer 2023.

Fernley Alt. U.S. 95/West Main Street (West Fernley Exit 46)• Alt. U.S. 95 reduced to one lane in each direction underneath I-80 at exit 46 beginning Jan. 16 through early summer 2023. 

Fernley U.S. 95A/Business I-80 (East Fernley Exit 48)• Southbound U.S. 95A is also scheduled to be closed underneath I-80 beginning this spring through fall 2023, with a local detour available. • Northbound traffic will still be able to travel through the underpass. 

Over-dimensional vehicles over 14-feet wide will not be able to travel the interstate or interchanges underneath the interstate in the area.

NDOT will rehabilitate and seismically retrofit four I-80 bridges at exit 48 (U.S. 95A), exit 46  (West Main Street), Vine Street Underpass in Fernley, and Exit 43 (Cantlon Drive/Main Street) in Wadsworth. The bridges were constructed in 1963 and are being seismically retrofitted for increased safety and longevity. The Main Street bridge in west Fernley will also be further rehabilitated by replacing aging pier cap joints with ultra high-performance concrete link slabs. The bridges are being renovated as part of NDOT’s continuing efforts to retrofit older bridges. Nevada bridges have been ranked as the nation’s best for eight years. 

Additional state highway information is available at dot.nv.gov or by calling (775) 888-7000. Also follow @NevadaDOTReno on Twitter for traffic and project updates in northern Nevada, and @nevadadot on Twitter, Facebook, and Instagram for updates from across the state.

Motorists should use caution while traveling through work zones, and take alternate detour routes, if possible. NDOT works with Waze to inform the public about planned highway restrictions. The schedule is subject to change due to weather or other factors. For the latest state highway conditions, visit nvroads.com or call 511 before driving.


Share
Rate

Comment

Comments

COMMENTS
Comment author: PFB Comment text: Why can't you guys find competent contractors.. For a large municipal facility like the indoor-outdoor Fernley Swimming Pool located at 300 Cottonwood Lane, a complete ground-up commercial build or major structural renovation typically spans 6 to 12 months or longer when factoring in large-scale engineering, public municipal permitting, specialized commercial HVAC/roofing, and health department inspections. The current renovation has been- The Fernley Swimming Pool has been closed for approximately six to seven months since late February 2026 for a major roof replacement and facility renovation. Now you sat October. Soooo 8 months for a new roof. The picture shows no other renovations. Comment publication date: 9/17/26, 7:14 PM Comment source: Electrical problem delays Fernley pool opening Comment author: P Comment text: Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS. Comment publication date: 9/16/26, 10:31 PM Comment source: Lift Station Failure Released Untreated Sewage Comment author: Christopher Walsh Comment text: Could you look into the strong recurring smell around Fernley? It smells like sewage and it can be bad enough that people don’t want to be outside or open their windows. It would be helpful to get an investigative journalist help the Fernley residents get a clear answer from the City, NDEP, and any involved facilities. I was really disappointed that the smell was not disclosed by my realtor when I moved here. I enjoy Fernley and am seeing the improvements that are being made. With Appreciation Comment publication date: 9/12/26, 2:49 PM Comment source: Sewage spill near City of Fernley Municipal Well 9 Comment author: Alicia Euresti Comment text: We are all so blessed to have Pastor Matt and Mrs. Regina in this town. They have become a major part of pur family and our children adore them. Thank you both for all you do for qll of us. We love you!!!! Comment publication date: 9/6/26, 9:24 PM Comment source: Fascinating Fernley: Meet Your Neighbors at Living Faith Food Pantry Comment author: R Conley Comment text: Is the deputy receiving any additional training or reinforcing prior training? Comment publication date: 9/5/26, 10:08 AM Comment source: Inmate escapes from Fernley substation Comment author: Kayla Allen Comment text: Suzie was a wonderful woman. I was pleased to call her my "godmother" as she helped me to become a better version of myself. I think about her a lot. Comment publication date: 7/10/26, 8:31 PM Comment source: Susanne Lynn Foster