Construction gearing up on the Truckee Canal Maintenance Project

Construction gearing up on the Truckee Canal Maintenance Project

By Rachel Dahl

On November 4, 2022, the Bureau of Reclamation and Truckee-Carson Irrigation District held an official ground-breaking ceremony according to a recent press release.

The project is funded through the Infrastructure Law and intends to restore safe, long-term operation of the Truckee Canal. The event marked the beginning of Phase 1 of a multi-phased construction project known as the Truckee Canal Extraordinary Maintenance Project. This first phase will line approximately 3.5 miles of the canal through the City of Fernley to provide structural integrity and community safety.

During heavy flooding in January of 2008, the canal breeched, flooding 590 homes in Fernley, and resulting several years later in an $8 million settlement from TCID.

Commissioner of the BOR, Camille Calimlim Touton attended the ceremony, saying, “The Truckee Canal modernization project reaffirms our commitment to making the investments necessary to safeguard community water supplies and revitalize water delivery systems.” She said the Infrastructure Law, along with the Inflation Reduction Act provides funding to invest in the nation’s western water and power infrastructure to the tune of $8.3 billion to Reclamation over five years to fund aging infrastructure projects.

According to the BOR press release, “This project will restore a sense of safety for the city of Fernley and will provide water supply reliability for farmers and irrigators throughout the region.

The City of Fernley filed a lawsuit last year, claiming that lining the canal would have a negative impact on the underground aquifer that supplies the municipal water supply, and cause over 70% of the domestic wells in the community to fail. Judge Miranda Du dismissed the lawsuit in December of 2021. The City appealed that decision to the U.S. 9th Circuit Court of Appeals.

Central Environmental Inc., a firm from Anchorage, Alaska has been awarded the BOR contract and the general contractor. In addition, there are several local sub-contractors who will complete work on the concrete lining of the ditch, build a new control buildings, and automated gage structures.

The canal was shut down in October for 12 months to accommodate the construction and no water deliveries to water right holders or to Lahontan Reservoir will be made until construction is completed, which is scheduled for October 2023.

Repayment of the $35 million contract between TCID and the BOR is currently at issue before the 10th Judicial District Court in Fallon, with Fernley filing a Motion to Intervene in the TCID request for Judicial Determination of Validity of the contract.


Share
Rate

Comment

Comments

COMMENTS
Comment author: Jack & Nancy CookComment text: Wonderful man. Created a precious family with Linda. Will always respect and admire his contribution to teaching at FHS.Comment publication date: 4/18/26, 10:27 AMComment source: Howard David JacksonComment author: JeffDickersonComment text: Very well reported, even though our motion was denied.Comment publication date: 4/15/26, 11:05 AMComment source: Judge allows Fernley City Council to proceed with corrective agenda item in Lau expulsion caseComment author: Todd fossumComment text: Hi my name is todd fossum i'm clarence's stepson, I was wondering if he had any siblings. I think he said he had a sister that just survived cancer. If she can get ahold of me or any buddy, my number is 916. 3 4 3 1 1 7 7.Thank you have a blessed dayComment publication date: 1/16/26, 4:33 PMComment source: Clarence L Shields C Comment author: Carl HagenComment text: So just curious, what is the point of a franchise agreement if it is not exclusive?Comment publication date: 12/15/25, 4:18 PMComment source: Council approves non-exclusive franchise agreement for waste collection C Comment author: Christine S GleasonComment text: In the first photo, the woman in the middle, wearing the black shirt, is SaraH Jean Gleason. She is not an FHS Leadership Student but is the person who is responsible (with the help of her father) for starting the Fernley Community Thanksgiving Dinner in 2011. She attended this year's dinner while home from Arizona State University, where she is working on her PhD.Comment publication date: 12/8/25, 8:52 PMComment source: About 400 meals served at Community Thanksgiving DinnerComment author: SusanComment text: RIP Sean. Prayers to the family, sorry for your loss.Comment publication date: 9/25/25, 1:11 PMComment source: Sean Everett Turner