Thacker Pass lithium mine appears to be better bet than Rhyolite Ridge site, head of NV's Dept. of Conservation & Natural Resources says

Thacker Pass lithium mine appears to be better bet than Rhyolite Ridge site, head of NV's Dept. of Conservation & Natural Resources says

Brad Crowell, Director of the Nevada Department of Conservation and Natural Resources, said on Nevada Newsmakers that the future looks brighter for the proposed lithium mine at Thacker Pass in Humboldt County than it does for the Rhyolite Ridge site in Esmeralda County.

"All the challenges related to Thacker Pass, from my perspective and my jurisdiction, are manageable," Crowell told host Sam Shad. "They just need to be managed."

Crowell did not exhibit the same enthusiasm for the Rhyolite Ridge project, although scientists say it holds the largest known lithium and boron deposits in North America.

A small desert plant which only grows on about 10 acres of land at the proposed mine site, called Tiehm's Buckwheat, is under consideration for the federal Endangered Species Act. Inclusion into the Act could block mining at the site.

The proposed mine would eventually destroy as much as 90 percent of the global population of the wildflower, according to published reports. Studies are underway at the University of Nevada, Reno, to see if the Tiehm's buckwheat can be transplanted. Yet so far, it has only thrived in the mineral-rich soil at the lithium-mine site.

"We don't yet know if the plant can be transplanted into new locations and be successful," Crowell said. "We're going through that process now. The feds, the companies are helping that research at UNR and the state is involved in it as well.

Veteran Nevadan Journalist Ray Hagar is known for fair and tough reporting and invigorating commentary.

"If we can prove out that you can trans-locate and propagate the plant and it can survive, and the mine can do its thing, great," Crowell said. "But we don't have that data yet. And until we do, (we can't) make those decisions. So I would tell folks to exercise patience and hopefully we can find science to allow for both of these things to move forward. But we don't know yet."

At Thacker Pass, Crowell sees a path to solve issues surrounding the mine, even though the mine has been fiercely opposed by environmentalists and Native American tribes.

"There is concern about water and contamination of the water table, so we've adjusted our permit from the state side to only allow extractions above the water table so we protect that," he said.

"The local committee is concerned about noise and truck traffic and things like that, which is legitimate," Crowell added. "They are working with the company to fund infrastructure that will help build new roads, move a school to a new location, so it is not burdened by these things. We'll be able to mitigate for sage grouse impacts. All of these things are manageable, if done correctly."

Proponents of the Thacker Pass mine scored a victory last Friday when federal judge Miranda Du ruled in Reno that preliminary digging at the site can proceed. The digging will help determine if the site holds historical and archaeological value to Native Americans.

In early 2022, Du is expected to rule on the broader question of whether the administration of former President Trump erred when it approved the project in January.

The stakes are high in Nevada's lithium debate since the mineral is critical for a clean-energy future that includes batteries to operate electric vehicles (EVs).

Nevada is poised to become an international lithium leader, Crowell said. Already, Tesla is building lithium-base batteries for its electric cars at its gigafactory at the Tahoe-Reno Industrial Complex east of Reno.

The American Battery Technology Company has broken ground on a 60,000-square-foot lithium-ion battery recycling facility in Fernley, according to published reports.The company would start out recycling 20,000 metric tons of lithium-ion batteries per year, before scaling up to handling 100,000 metric tons annually.

The latter amount alone would match the number of lithium-ion batteries that were recycled in all of 2018 globally, according to London-based Circular Energy Storage.

"Lithium, from my perspective, is one of the great emerging economic stories for Nevada that will really be a benefit if we can leverage it correctly," Crowell said. "We have a unique ability, compared to other states, to have the full economic lifecycle for lithium, from extraction to production in batteries to recycling it back into the supply chain. And we have all three of those components here."

Watch this episode of Nevada Newsmakers.

See the upcoming schedule of Nevada Newsmakers.


Share
Rate

Comment

Comments

COMMENTS
Comment author: John Mueller Comment text: FERNLEY’S WATER EMERGENCY: FIVE QUESTIONS STILL NEED ANSWERS The November 12 Fernley Reporter article provides a good recap of the November 3 water emergency and the November 4 City Council meeting. First, credit where credit is due. Our city employees responded, restored operations, and took precautions to protect residents. That’s important and appreciated. But fixing the immediate problem isn’t the same as preventing it from happening again. There are five reasonable questions our community deserves answers to: 1. WHAT ACTUALLY FAILED? What was the root cause of the water treatment plant’s communication failure, and why didn’t the backup systems prevent the interruption? 2. HOW CLOSE WERE WE TO A REAL EMERGENCY? How much usable water remained in storage, and how close did we come to affecting essential services, including firefighting? 3. WHAT WILL THIS COST TAXPAYERS AND RATEPAYERS? What did the emergency cost, what additional repairs or upgrades are necessary, and how will they be funded? 4. WHO IS RESPONSIBLE FOR MAKING SURE IT DOESN’T HAPPEN AGAIN? Is there a written corrective-action plan with assigned responsibilities, measurable results, and completion deadlines? 5. HOW WILL RESIDENTS KNOW THE PROBLEM IS REALLY FIXED? Will the city publish an after-action report explaining what happened, what was learned, what has been corrected, and what still needs attention? This isn’t about pointing fingers or finding someone to blame. It’s about learning, improving, and protecting our community. We can appreciate the city’s response while still expecting transparency, accountability, and a commitment to continuous improvement. Some technical information may need to remain confidential for security reasons. But that shouldn’t prevent residents from understanding the risks, the corrective actions, and the results. The real question isn’t whether Fernley recovered from the November 3 emergency. We know it did. The question is: If the same failure happened tomorrow, would we be better prepared? That’s a conversation worth having. Our community deserves more than reassurance. It deserves measurable results. Comment publication date: 11/12/26, 1:54 PM Comment source: Fernley Council Addresses Water Emergency Comment author: Donald DeVold Comment text: Great article It’s actually spelled DeVold Thank you Comment publication date: 10/29/26, 4:58 PM Comment source: The great robbery: Strip-6 by Solis helps Vaqueros punch playoff ticket Comment author: CH Comment text: I want to start a betting 'pool' for the October, November, and December closures: 1. A dent in the pool slide. 2. A failed breaker. 3. A pebble loose in the water part (replacing all concrete) 4. Hurricane Polo makes a sudden turn and blows off the roof (again). With soft muscles after 7 months of no swimming, the only health left is my sense of humor :) Comment publication date: 10/1/26, 11:18 AM Comment source: Fernley Pool Renovation Moves Forward, One Test at a Time Comment author: PFB Comment text: Why can't you guys find competent contractors.. For a large municipal facility like the indoor-outdoor Fernley Swimming Pool located at 300 Cottonwood Lane, a complete ground-up commercial build or major structural renovation typically spans 6 to 12 months or longer when factoring in large-scale engineering, public municipal permitting, specialized commercial HVAC/roofing, and health department inspections. The current renovation has been- The Fernley Swimming Pool has been closed for approximately six to seven months since late February 2026 for a major roof replacement and facility renovation. Now you sat October. Soooo 8 months for a new roof. The picture shows no other renovations. Comment publication date: 9/17/26, 7:14 PM Comment source: Electrical problem delays Fernley pool opening Comment author: P Comment text: Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS. Comment publication date: 9/16/26, 10:31 PM Comment source: Lift Station Failure Released Untreated Sewage Comment author: Christopher Walsh Comment text: Could you look into the strong recurring smell around Fernley? It smells like sewage and it can be bad enough that people don’t want to be outside or open their windows. It would be helpful to get an investigative journalist help the Fernley residents get a clear answer from the City, NDEP, and any involved facilities. I was really disappointed that the smell was not disclosed by my realtor when I moved here. I enjoy Fernley and am seeing the improvements that are being made. With Appreciation Comment publication date: 9/12/26, 2:49 PM Comment source: Sewage spill near City of Fernley Municipal Well 9