CRRC construction on pace for July 3 completion

CRRC construction on pace for July 3 completion
Mayor Neal McIntyre speaks during the Oct. 4 topping off ceremony. (Photo courtesy of City of Fernley)

Robert Perea, The Fernley Reporter

Construction on the first phase of the Community Response and Resource Center is roughly 33 percent complete and on schedule to be completed next July, according to a report presented at the Oct. 16 meeting of the Fernley City Council.

Mike Allen, senior project manager for the Cumming Corporation, the city’s representative for the CRRC, presented the city with an update of the costs to date and the progress of construction. He said according to the numbers through the end of September, work completed was $5,452,095.49 of the $17,765,798 budget.

The city held a topping off ceremony on Oct. 4 to mark the placement of the final steel beam in the building. Allen said having all the pavement down and the topping off are key milestone dates for the construction.

Allen also said they haven’t yet used any of the 15 weather days that were built into the schedule, although they expect to in winter and spring.

That 33 percent of work completed includes the site work, which if finished except for grading around the building, and landscaping. He said the structure itself is almost done, and the enclosure is the next phase.

“That’s one of the key components we’re trying to shoot for, I think December, to have the roof on and the building essentially dried so we can continue with framing and mechanical plumbing,” he said.

He said that 33-percent completion should go up another 5 to 10 percent through November.

“Schedule wise, we’re on schedule,” Allen said. “We’re still on target.”

Share
Rate

Comment

Comments

COMMENTS
C Comment author: Carl C. Hagen Comment text: Maybe there is more to this story than what is reported, but it seems to me that the businesses that are causing this problem ought to be paying for this, or at least a major portion of it. Why does the County have to pay the whole bill? Just my opinion. Comment publication date: 5/7/26, 10:26 AM Comment source: Storey County, Tesla partner to extend I-80 Patrick on-ramp Comment author: Alan Reeder Comment text: Great guy, laughed easily, had fun with his students, enjoyed our time together at FHS! Comment publication date: 4/23/26, 10:23 PM Comment source: Howard David Jackson Comment author: Jack & Nancy Cook Comment text: Wonderful man. Created a precious family with Linda. Will always respect and admire his contribution to teaching at FHS. Comment publication date: 4/18/26, 10:27 AM Comment source: Howard David Jackson Comment author: JeffDickerson Comment text: Very well reported, even though our motion was denied. Comment publication date: 4/15/26, 11:05 AM Comment source: Judge allows Fernley City Council to proceed with corrective agenda item in Lau expulsion case Comment author: Todd fossum Comment text: Hi my name is todd fossum i'm clarence's stepson, I was wondering if he had any siblings. I think he said he had a sister that just survived cancer. If she can get ahold of me or any buddy, my number is 916. 3 4 3 1 1 7 7.Thank you have a blessed day Comment publication date: 1/16/26, 4:33 PM Comment source: Clarence L Shields C Comment author: Carl Hagen Comment text: So just curious, what is the point of a franchise agreement if it is not exclusive? Comment publication date: 12/15/25, 4:18 PM Comment source: Council approves non-exclusive franchise agreement for waste collection