CRRC construction on pace for July 3 completion

CRRC construction on pace for July 3 completion
Mayor Neal McIntyre speaks during the Oct. 4 topping off ceremony. (Photo courtesy of City of Fernley)

Robert Perea, The Fernley Reporter

Construction on the first phase of the Community Response and Resource Center is roughly 33 percent complete and on schedule to be completed next July, according to a report presented at the Oct. 16 meeting of the Fernley City Council.

Mike Allen, senior project manager for the Cumming Corporation, the city’s representative for the CRRC, presented the city with an update of the costs to date and the progress of construction. He said according to the numbers through the end of September, work completed was $5,452,095.49 of the $17,765,798 budget.

The city held a topping off ceremony on Oct. 4 to mark the placement of the final steel beam in the building. Allen said having all the pavement down and the topping off are key milestone dates for the construction.

Allen also said they haven’t yet used any of the 15 weather days that were built into the schedule, although they expect to in winter and spring.

That 33 percent of work completed includes the site work, which if finished except for grading around the building, and landscaping. He said the structure itself is almost done, and the enclosure is the next phase.

“That’s one of the key components we’re trying to shoot for, I think December, to have the roof on and the building essentially dried so we can continue with framing and mechanical plumbing,” he said.

He said that 33-percent completion should go up another 5 to 10 percent through November.

“Schedule wise, we’re on schedule,” Allen said. “We’re still on target.”

Share
Rate

Comment

Comments

COMMENTS
Comment author: CH Comment text: I want to start a betting 'pool' for the October, November, and December closures: 1. A dent in the pool slide. 2. A failed breaker. 3. A pebble loose in the water part (replacing all concrete) 4. Hurricane Polo makes a sudden turn and blows off the roof (again). With soft muscles after 7 months of no swimming, the only health left is my sense of humor :) Comment publication date: 10/1/26, 11:18 AM Comment source: Fernley Pool Renovation Moves Forward, One Test at a Time Comment author: PFB Comment text: Why can't you guys find competent contractors.. For a large municipal facility like the indoor-outdoor Fernley Swimming Pool located at 300 Cottonwood Lane, a complete ground-up commercial build or major structural renovation typically spans 6 to 12 months or longer when factoring in large-scale engineering, public municipal permitting, specialized commercial HVAC/roofing, and health department inspections. The current renovation has been- The Fernley Swimming Pool has been closed for approximately six to seven months since late February 2026 for a major roof replacement and facility renovation. Now you sat October. Soooo 8 months for a new roof. The picture shows no other renovations. Comment publication date: 9/17/26, 7:14 PM Comment source: Electrical problem delays Fernley pool opening Comment author: P Comment text: Relative of the Mayor is to over see this site. Anyone who knows Fernley KNOWS this is more of the who you are related to and know business in this town. VOTE THEM ALL OUT AND THE CALIFORNIA TRANSPLANTS. Comment publication date: 9/16/26, 10:31 PM Comment source: Lift Station Failure Released Untreated Sewage Comment author: Christopher Walsh Comment text: Could you look into the strong recurring smell around Fernley? It smells like sewage and it can be bad enough that people don’t want to be outside or open their windows. It would be helpful to get an investigative journalist help the Fernley residents get a clear answer from the City, NDEP, and any involved facilities. I was really disappointed that the smell was not disclosed by my realtor when I moved here. I enjoy Fernley and am seeing the improvements that are being made. With Appreciation Comment publication date: 9/12/26, 2:49 PM Comment source: Sewage spill near City of Fernley Municipal Well 9 Comment author: Alicia Euresti Comment text: We are all so blessed to have Pastor Matt and Mrs. Regina in this town. They have become a major part of pur family and our children adore them. Thank you both for all you do for qll of us. We love you!!!! Comment publication date: 9/6/26, 9:24 PM Comment source: Fascinating Fernley: Meet Your Neighbors at Living Faith Food Pantry Comment author: R Conley Comment text: Is the deputy receiving any additional training or reinforcing prior training? Comment publication date: 9/5/26, 10:08 AM Comment source: Inmate escapes from Fernley substation